Boise, ID
Boise VAMC
Chiller Rebalance and System Evaluation
GDM provided professional engineering services for the evaluation of existing chilled water systems. While the original scope of work for the project was to re-balance the chilled water systems in Building 67, it was discovered during the initial phase of the project that there was little to now existing accurate documentation of the existing systems, and therefore nothing to base rebalancing recommendations on. The scope of the project was redirected to perform site investigations to locate and document the existing chilled water systems in the building, and then to provide the VA with an up-to-date set of documentation showing actual locations and sizes of piping, valving, and equipment.